LEAD TIME INTELLIGENCE TERMINALv2026.Q1 · POWER EQUIPMENT · US UTILITIES
SESSION ————-—— ——:——:——ZLIVE
QOQ MOVERS · 2026-Q1
Auto 345kV-5wksPT 138kV-3wksAIS 69–138-3wksGSU 500kV+-2wksAuto 230kV-2wksMobile Sub-2wksGIS 138–230kV-2wksMV Recloser-2wksGIS 345kV+-1wksAIS DT 138–230-1wksAuto 345kV-5wksPT 138kV-3wksAIS 69–138-3wksGSU 500kV+-2wksAuto 230kV-2wksMobile Sub-2wksGIS 138–230kV-2wksMV Recloser-2wksGIS 345kV+-1wksAIS DT 138–230-1wks
Median Lead Time
97wks
2026-Q1 · all sub-classes
YoY Median Δ
-9wks
vs Q1 2025
Confidence ≥ A
70%
7/10 sub-classes
Worsening QoQ
0of 10
sub-classes
LTM/01Lead Time Matrix
Sub-ClassCurrent (wks)P25 – P75Δ QoQΔ YoY12mo FCConfSuppliersTop-3 Share
GSU 500kV+
≥500 kV, ≥500 MVA, generator step-up
159135183-2-10140B678%
Auto 345kV
345/138 kV, 300–600 MVA
133114152-5-11118A968%
GIS 345kV+
Gas-insulated, ≥345 kV bay
121104138-1-9108B491%
Auto 230kV
230/69 kV, 150–300 MVA
11197125-2-795A1258%
GIS 138–230kV
Gas-insulated, 138–230 kV
9784110-2-684A676%
PT 138kV
138/13.8 kV, 28–84 MVA
847395-3-1274A1452%
AIS DT 138–230
Air-insulated, SF6 dead-tank
746583-1-964A962%
Mobile Sub
Trailer-mounted, ≤30 MVA, 69–138 kV
685680-2-1060B582%
AIS 69–138
Air-insulated, live-tank
564963-3-850A1155%
MV Recloser
Distribution-class, 15–38 kV
353040-2-630A1361%
Source: LTI proprietary aggregation of utility procurement quotes, OEM order-book disclosures, EEI surveys, and trade press. Lead time = weeks from PO to ex-works.