LEAD TIME INTELLIGENCE TERMINALv2026.Q1 · POWER EQUIPMENT · US UTILITIES
SESSION ————-—— ——:——:——ZLIVE
QOQ MOVERS · 2026-Q1
Auto 345kV-5wksPT 138kV-3wksAIS 69–138-3wksGSU 500kV+-2wksAuto 230kV-2wksMobile Sub-2wksGIS 138–230kV-2wksMV Recloser-2wksGIS 345kV+-1wksAIS DT 138–230-1wksAuto 345kV-5wksPT 138kV-3wksAIS 69–138-3wksGSU 500kV+-2wksAuto 230kV-2wksMobile Sub-2wksGIS 138–230kV-2wksMV Recloser-2wksGIS 345kV+-1wksAIS DT 138–230-1wks
PRJProject Definition
Project Name
Required In-Service Date (RIS)
EQPEquipment Line Items
Sub-ClassQtyReview (wks)Shipping (wks)FC LeadTotal WksOrder By (P50)Risk
230/69 kV, 150–300 MVA
951072027-06-03OK
Gas-insulated, 138–230 kV
84922027-09-16OK
Air-insulated, live-tank
50562028-05-25OK
GNTProcurement Timeline
SUB-CLASS
2027-03-11
RIS · 2029-06-21
DAYS TO ORDER
Auto 230kV
×2
347d
GIS 138–230kV
×4
452d
AIS 69–138
×6
704d
Bar span = P25–P75 lead time uncertainty. Solid fill = procurement window. Solid right edge = RIS date. Recommend issuing PO no later than the P50 (center) date. Calculation: Order By = RIS − (12-mo forecast lead time + internal review + shipping).