PRJProject Definition
Project Name
Required In-Service Date (RIS)
EQPEquipment Line Items
| Sub-Class | Qty | Review (wks) | Shipping (wks) | FC Lead | Total Wks | Order By (P50) | Risk | |
|---|---|---|---|---|---|---|---|---|
230/69 kV, 150–300 MVA | 95 | 107 | 2027-09-05 | OK | ||||
Gas-insulated, 138–230 kV | 84 | 92 | 2027-12-19 | OK | ||||
Air-insulated, live-tank | 50 | 56 | 2028-08-27 | OK |
GNTProcurement Timeline
SUB-CLASS
2027-06-13
RIS · 2029-09-23
DAYS TO ORDER
Auto 230kV
×2
346d
GIS 138–230kV
×4
451d
AIS 69–138
×6
703d
Bar span = P25–P75 lead time uncertainty. Solid fill = procurement window. Solid right edge = RIS date. Recommend issuing PO no later than the P50 (center) date. Calculation: Order By = RIS − (12-mo forecast lead time + internal review + shipping).